Our community golf course is nearing completion! 

All hole shaping is finished, and the entire golf course has been fully grassed and sprigged. A special thank you and congratulations to all of our partners who have played a vital role in bringing this beautiful golf course to life.

Grow-in of the golf course continues with our talented agronomy team actively nurturing, mowing, irrigating, and refining the turf over the coming months to prepare it for play. We want to recognize our superintendent, Michael Shafer, and assistant superintendent, Zachary Allen, for their leadership, hard work, and care throughout the build and the grow‑in process. 

Village Construction Update

Work is also progressing rapidly at the site of our amenity village. The aerial image below provides an overview of all of our amenities.

From left to right are the First Tee Academy, The Pavilion outdoor bar, The Gimme concessions area, the Cart Barn, the Golf Shop, and Oakwood Grill overlooking the water, with the practice range located in the foreground.

Additional photos below highlight ongoing construction progress, including steel framing and exterior sheathing installation at Oakwood Grill, The Pavilion, and The Gimme.

Our continued thanks go to all of our partners, contractors, and teams whose dedication and expertise are bringing The Gate Golf Club to life.

For more information, contact info@thegategolf.org and follow The Gate Golf Club on Instagram, Facebook and LinkedIn.

News

As the year draws to a close, the course is taking on its final form. Crews are shaping key golf course features on the remaining holes—1 and 9—while additional grass coverage, landscaping, and finishing details will be added across the course in the months ahead.

At the Village area, some of the course’s most memorable views are coming to life, with the lakefront Oakwood Grill set to become a true standout. Buildings are rising and netting pole bases are now being set at the practice range. 

In the coming months, we’ll be sharing new opportunities to join our growing team. Be sure to visit our Career Opportunities page to learn more—we’d love to connect with you.

Looking Back on the Year

As we reflect on an incredible year of growth and development, we are deeply grateful to the partners and community members who have shared their time, talent, and expertise to help bring The Gate Golf Club to life.

As a 501(c)(3) public charity, The Gate Golf Club is dedicated to making the game of golf more accessible by offering a public 9-hole golf course and practice complex for families, children, and players of all skill levels throughout Southwest Florida.

With gratitude to our partners:

🤝 Founding Partners:
Collier County | The Gate Golf Club, Inc. | First Tee – Naples/Collier

🎨 Design:
MHK Architecture | Jacobsen Hardy Golf Design | Freestyle Interiors

📐 Development:
Arthrex, Inc. | LJA Engineering | Jenkins Maag Associates | Hellman & Partners, LLC

🏗️ Construction:
DeAngelis Diamond | Glase Golf Construction

🎥 Media:
Arthrex StudioX (Video Content) | SMITH Media & Design (Logo Design) | MG-IP Law (Trademark Services)

Thank you for being part of this journey. Here’s to an exciting year ahead!

For more information, contact info@thegategolf.org and follow The Gate Golf Club on Instagram and Facebook.

News

Here’s an update on progress made during November!

Course and Village Construction Update 

We hope everyone enjoyed a wonderful Thanksgiving! We’re very grateful to our project partners for the tremendous progress at The Gate Golf Club.

The majority of the course is now sodded, and sprigging of the putting greens with TifEagle bermudagrass and the remaining fairways with Celebration bermudagrass will begin in early December.

Within the Village construction site, masonry walls rose across multiple buildings, giving the area greater definition, while structural steel is progressing at the Oakwood Grill restaurant. 

At the same time, structural steel and metal roofing were installed at the Maintenance and Environmental buildings, which are on track to be completed next month. 

Looking ahead, the driving range netting poles will be installed, giving the site a true driving-range appearance and providing a clearer picture of the facility’s final layout.

Site Visit from Florida Gulf Coast University (FGCU) Students 

We had the pleasure of hosting students from the Florida Gulf Coast University PGA Golf Management Program (PGM) for an educational site visit. The field day provided an excellent opportunity to showcase how this course, designed by Peter Jacobsen and Jim Hardy, is being built with a focus on challenge, playability, and environmental sensitivity.

The students spent the day learning from our Superintendent, Mike Shafer, and our team about golf course construction and how this project will create more opportunities for people to enjoy golf. They gained hands-on insight into course feature shaping, irrigation and drainage systems, earthwork and lake development, and the sustainable practices we use to ensure the course is both high-quality and environmentally responsible.

For more information, contact info@thegategolf.org and follow The Gate Golf Club on Instagram and Facebook.

News

The golf course is coming to life! This month brought incredible progress as holes 4 through 8 are now sodded and a vibrant shade of green. Crews have been working efficiently to install sod during the warm season, taking advantage of ideal growing conditions to promote strong turf establishment and coverage.

Grading has begun at the driving range, which will measure approximately 320 yards in length and feature Celebration Bermudagrass in the landing area. The tee line will be a one-story facility, designed for both functionality and a premium player experience.

Meanwhile, things are taking off at the Village site — building foundations are being poured, and walls are going vertical! At the future home of Oakwood Grill, stem walls and columns are taking shape, while footers are complete at The Pavilion, pro shop, and The Gimme concessions area — huge milestones as each unique space starts to come to life.

Located between holes 3 and 7, the Maintenance and Environmental Buildings have now had their concrete slabs poured. These facilities will provide essential support for daily course operations, equipment maintenance, and environmental management initiatives.

Concrete cart paths are now complete alongside holes 4, 5 and 6. The course will include continuous paths throughout, yet it’s also been thoughtfully designed for walking — giving players the flexibility to enjoy their round on foot or by cart.

Thank you to everyone who’s played a role in this progress — from our construction teams and partners to the community following along with us!

For more information, contact info@thegategolf.org and follow The Gate Golf Club on Instagram and Facebook.

News

Page Footer

About Us

Privacy Policy

The Gate Golf Club opens to the public in 2026!

Contact

Email: info@thegategolf.org

  • Facebook
  • Instagram
Copyright © 2026 The Gate Golf Club All Rights Reserved.
Powered by Powered by Golf Channel Solutions

The Gate, Oakwood Grill, and the Tree Logo are trademarks of The Gate Golf Club, Inc. First Tee and associated logos are federally registered trademarks owned by PGA TOUR First Tee Foundation, Inc.